Forestry mulching, underbrushing and land clearing across Monticello and Jefferson County. One machine cuts, grinds and spreads in a single pass, so nothing is piled, burned or hauled off your place.
- Priced from photographs, usually same day
- Four acres cleared in one machine day, Dec 2023
- From $3,000 a machine day
What we clear in Monticello
Eight things we are actually asked for on Jefferson County ground. If your job is not on this list, say so and we will tell you straight whether it is ours.
One machine cuts standing growth and grinds it back into the ground as chip in the same pass. No pile, no burn, no trucks.
Privet, briar and yaupon taken out from under the live oaks and hardwoods you are keeping. The usual brief on old home ground here.
Ground that has come out of use and gone to scrub, put back to something you can mow, graze or build on.
You mark what stays and we cut round it. In this county the old live oaks are usually the whole point of the property.
A line you can run wire along or walk, cut without disturbing what is either side.
Where the roots have to come out rather than the top growth being ground off. Our 30 inch excavator mulcher.
Building envelope, drive and pad taken down to workable ground before your builder arrives.
Rides through a block, food plot lanes, and a cut line between your buildings and the timber.
Who calls us in Jefferson County
Ground round a house that has been in the family a while, where the understory has closed in and the oaks are worth protecting.
Jefferson has real hills by Florida standards. Ground that has gone to scrub on a slope is awkward to mow and easy to mulch.
Rides, food plot lanes and blocks where the understory has closed in since the last thin.
Clearing the envelope, the drive and the pad before the builder mobilises, so the site is ready rather than a delay.
A parcel nobody can see across is a parcel nobody buys. A machine day usually shows the buyer what they are actually looking at.
Ground held from out of county that needs keeping walkable without you having to be there.
How the work runs
Four steps, and the first two happen before anything leaves our yard.
Pictures with something in frame for scale, the parcel size, and a note on what you want left standing. On rolling ground a shot from the low side tells us more than one from the top.
Usually the same day. It is a day count against a published rate, not a guess dressed up as a quote. Jefferson has run well for us so far.
The mulching head cuts, grinds and spreads as it goes. No separate clear, pile and haul stage, which is where most of the cost and all of the mess normally sits.
Not bare clay and not a field of cut stems. On a slope that chip layer is doing real work holding the surface where it is.
Photographs from our jobs
Photographs from jobs we have run. Nothing here is stock photography and nothing here is generated.




What it costs
We sell machine days, not acres, and we publish the rates. Jefferson has been good ground for us: four acres came down in one machine day in December 2023, which is about as much as a day covers anywhere.
Stems to 8 inches. Transport included. The machine for a home place or a paddock edge
Stems to 30 inches, and grubbing. Plus transport
Stems to 24 inches. Plus transport. The dearest machine we run
What moves the day count
The rate follows the machine rather than the size of the stem, which catches people out: the dedicated mulcher costs more than the excavator even though the excavator takes bigger timber and pulls roots. Transport is the cost of getting the bigger two machines to you and is separate from hauling material away, which is quoted per job.
What we have actually done in Monticello
Four finished jobs and five machine days, from December 2023 to September 2025. Monticello is the whole of our Jefferson County record, so this is all of it.
| Dec 2023 | Four acres, 1 machine day. The largest here and still a single day |
| Apr 2024 | An acre and a half, 1 machine day |
| Apr 2025 | One acre, 2 machine days |
| Sep 2025 | Three quarters of an acre, 1 machine day |
Three of the four were single machine days, and the largest of them was four acres. The one that took two days was a single acre in April 2025, which is the same lesson this whole county teaches: what is standing matters more than how much ground it stands on. Only one of the four recorded a machine, and that job ran with the skid steer mulcher.
The ground on a Jefferson County parcel
| What grows here | Live oak, hickory and pine on the clay hills, with privet, yaupon and briar filling the understory wherever grazing or mowing has stopped. Bottomland hardwood along the creeks. This is red hills country rather than Florida flatwoods |
| What that means for a machine | Privet mulches quickly and the open oak ground works fast, which is how four acres came down in a day. Old hedgerow and creek bottom are the slow parts |
| Soil and slope | Clay rather than sand, and genuinely rolling by Florida standards. Clay holds water at the surface after rain, so a wet week here matters more than it would on sand, and slope is worth mentioning when you send photographs |
| Access | Rural roads and farm gates, generally wide. Distance is the thing that shows up as transport rather than as day count, since this is the far north of the state |
Cleared in a single machine day in Monticello, December 2023. On open red hills ground a day covers more than most people expect.
What customers say
FloridaLandClearing.com was beyond helpful in getting our property cleared. They were spot on with their quote, their crews arrived on time, and the machines they used were impressive to watch.
Jenny AndersonWe had a difficult project a few other companies attempted and left. Florida Land Clearing was able to get the job done and a day earlier than quoted.
Joseph KellyThese guys are pros. Watching these machines just devour acres of underbrush in a day was one of the coolest things I have seen. I cannot believe how this transformed my property.
Adam WilsonBefore you book: trees on a Jefferson County parcel
Jefferson County is rural and much of the land here is in timber or agricultural use, which is treated differently from a residential lot inside Monticello.
Silvicultural work under an approved forestry practice is generally handled differently from clearing for development, and the rules for a lot in town are not the ones for a timber block outside it. Live oaks of any size tend to attract more attention than understory growth.
Tell us what you want gone and what you want kept when you send photographs. If the parcel is in agricultural or timber use, say so, because it changes which questions are worth asking.
We are a clearing contractor, not the permit office, and we do not file applications. Confirm your own parcel and your own trees with Jefferson County or the City of Monticello before you commit.
Monticello questions
How much does it cost to clear land in Monticello?
From $3,000 a machine day. Three of our four Jefferson County jobs were single days, including a four acre parcel, so one day is a fair starting assumption on open ground. Send photographs and we will give you a day count.
How long does it take?
Three of four were one machine day. The exception was a single acre in April 2025 that took two, because of what was standing on it rather than its size. We will tell you which kind yours looks like before you book.
Can you work on a slope?
Yes, and there is more slope here than most of Florida. Tracked machines handle it. What matters is how wet the clay is, so a rainy week moves the schedule more than the terrain does.
Will you leave the live oaks?
Yes, and in this county we would usually advise it. Mark them before we come out. A mulcher going round a tree is slower than one going through it, so selective work can add day count, and we will say so when it does.
What happens to everything you cut?
It stays on the ground as mulch, spread as the machine goes. Nothing piled, nothing burned. On clay slopes that layer holds the surface where it is instead of letting it move in the next storm.
Do I need a permit?
It depends on the species and size of what is standing, on whether you are inside Monticello, and on how the land is classified. Confirm with the right office rather than taking a contractor word for it, ours included.
Are you licensed and insured?
Insured, and we send the certificate before the machine moves. Florida does not issue a contractor licence for forestry mulching, so nobody holds one. Insurance is the document worth asking every contractor to produce.
Around Monticello
Get a price on your Monticello lot
Send a few photographs, the parcel size and a note on what you want left standing. Mark the live oaks you want kept and we will price the job round them.